Working hard to ensure a safe, secure and reliable power supply for our customers now and in the future.

E whakapau kaha ana kia whakaū mai tētahi tukunga hiko haumaru, tukunga tūwhita, tukunga tūtika mā ō mātou kiritaki i nāianei, ā, ko muri atu anō.

Netwk proj map

1. INTERCONNECTION - RANGIAHUA AND SOUTH ROAD (STAGE 2)
STATUS: PLANNING
This project will create smaller sections of lines using remote control switches to reduce the number of customers affected during faults, and shorten the time it takes to locate a fault.
We will also look at how we can provide an alternative source of supply interconnecting the South Road and Rangiahua distribution lines. Completion of this project is expected during
October 2025.

1. TE TŪHONONGA O RANGIAHUA ME SOUTH RD (KAUPAE 2)
TE ĀHUA: E WHAKAMAHERE ANA
Ko te kaupapa nei e hanga i ngā wāhanga nōnohi ki ngā taura hiko mā ngā rou mamao, kia whakaheke ai te nui o ngā kiritaki e pāngia ana ki ngā kotinga hiko, ā, kia wawe tonu nei te kite i ngā whatinga. Ko te rapu atu anō mātou, e pēhea te tuku he hiko kē atu, rā te tūhono i ngā taura kawe hiko i South Rd ki Rangiahua. E oti te kaupapa nei, ā te Oketopa rā anō, 2025.

2. SANDHILLS RD-HEREKINO & AWANUI HIGH VOLTAGE DISTRIBUTION LINES
STATUS: CONSTRUCTION
Sandhills Road project enables the interconnection between Awanui and Herekino. It will upgrade the existing line on Sandhills Road, and extend a new line to complete the
interconnection. Apart from improving resilience, it allows for the backfeeding of supply from an alternate direction, resulting in fewer customers being without power during both planned and unplanned outages. Completion of this project is expected during July 2025.

2. NGĀ TAURA KAWE HIKO KAHA I SANDHILLS ROAD, HEREKINO KI AWANUI
TE ĀHUA: E MAHI ANA
Mā te kaupapa i Sandhills Road, e āhei ai te tūhononga i waenganui i Awanui ki Herekino. Ka whakahou ngātahi i ngā taura hiko e rua i Sandhills Road, ka tāpirihia atu ai tētahi taura hou atu anō e oti ai te tūhononga. Tua atu i te whakakaha, i te whakaūnga, e āhei ana ki te tuku whakamuri i ahunga kē atu, e hua ai kia iti ake nei ngā kiritaki e noho hiko kore ana, ā te wā o ngā kotinga hiko ohorere, i ngā kotinga hiko ko whakaritea nōki. E oti te kaupapa nei, ā te Hūrae rā anō, 2025.

3. OMANAIA 33KV SUB - TRANSMISSION LINE REFURBISH (STAGE 7)
STATUS: ESTIMATING
The Omanaia 33kV sub-transmission line is the sole source of power supply to Omanaia. To increase flexibility and security to the power supply in this area, we are going to refurbish the 33kV line by replacing power poles, cross arms, and line hardware improving the reliability of this line. Stage 7 will address 59 structures. Completion of this project is scheduled for April 2026.

3. TE WHAKAHOU I TE OMANAIA 33KV TAURA KAWE HIKO NOHINOHI NEI (KAUPAE 7)
TE ĀHUA: E WHAKATAU TATA ANA
Ko te Omanaia 33kV taura kawe hiko nohinohi nei, ko te kawenga hiko nahe anō ki Omanaia. Kia whakarahi ake i te ngāwari me te mau o te tukunga hiko ki tēnei rohe, ka whakahoungia e mātou te taura 33kV, ka whakakapi i ngā pou hiko, i ngā kaho, me ngā taputapu taura kia kaha ake ai te whakaūnga o te taura nei. Ko te Kaupae 7, e aro ki ngā hanganga 59. E oti te kaupapa nei, ā te Aperira rā anō, 2026.

4. INTERCONNECTION - MATAURI BAY AND WHANGAROA LINES CONDUCTOR UPGRADE (STAGE 2)
STATUS: PLANNING
The commissioning of the newly constructed Whangaroa – Matauri Bay 11kV Interconnections prompted the need to upgrade sections of the overhead line to increase the current carrying capacity as well as improving the reliability of the line. Completion of this project is planned for April 2026

4. HE TŪHONONGA - NGĀ PŪKAWE I MATAURI ME WHANGAROA
TE ĀHUA: E WHAKAMAHERE ANA
Nā te tono i te tūhononga hou o Whangaroa – Matauri, 11kV, i toko ake te hiahia kia whakahoungia ētahi wāhanga o ngā taura hiko o runga, kia whakarahi ake i te raukaha kawe hiko, ā, hei whakakaha tonu i te whakaūnga o te taura rā. E oti te kaupapa nei, ā te Āperira rā anō, 2026.

5. UNDERGROUND OMANAIA SUB-TRANSMISSION LINE
STATUS: CONSTRUCTION
During the Omanaia rebuild some risks such as dual lines on a single structure out of the substation were identified for the security of power supply to the South Hokianga area. This project undergrounds these lines and upgrades the switchgear at the Omanaia substation to enable security and alleviate constraints. Construction is planned for Summer 2026

5. TE TAURA KAWE HIKO NOHINOHI I TE WHENUA I OMANAIA
TE ĀHUA: E MAHI ANA
Nō te whaakahounga o Omanaia i kitea ake ai ētahi tūraru e mau ai te tukunga hiko ki
Hokianga ki te tonga, pērā i ngā taura hiko takirua ko runga i tētahi hanganga kotahi e puta atu ana i te wāhi punahiko raka. Ko te kaupapa nei e tuku atu ngā taura hiko i te whenua, ka whakahoungia ai ngā pana i te wāhi punahiko i Omanaia kia ū ai te mau o te hiko, ā, kia heke ai ngā kōpiringa. Hei te raumati rā āno, 2026 timata ai tēnei kaupapa.

6. 110KV UPGRADE – WIROA SUBSTATION
STATUS: DESIGN
Wiroa substation is undergoing extension and upgrade work to support capacity growth in the area and voltage regulation to the eastern coastline. The upgrade will commence in October 2025 with final completion in 2029.

6. TE WHAKAHOU I TE 110KV - WIROA, WĀHI-PUNAHIKO
TE ĀHUA: E WHAKAAHUA ANA
E whakarahi ake ana, e whakahou ana nōki i te wāhi-punahiko i Wiroa, kia pai ake ai te
tupuranga o te tukunga hiko ki Te Tai Tamawahine. Hei te Oketopa, 2025, timata ai te whakahou, ka oti rā anō ai ā te tau 2029.